The goal of the DIWICON-S preventive safety system is to detect and help localize
activity occurring above a pipeline. This is achieved by installing a preventive
safety cable along the entire length of a pipeline.
Operation
The marker band has a layered structure. Its upper layer is a high visibility
marker sheet and the lower layer is a sheet of geotextile. Between the marker
sheet and the geotextile sheet are two specially insulated twin strand cables
(DW 131 S) laid out in a sine wave pattern. 20 cm of insulated cable (DW 131 S)
extends from the ends of the marker band (DW 135 S), for repair and connection purposes.
Connection options:
- Passive joint
- Active joint unit (DW 137 S)
- Carpet junction cable (DW 239 S)
After being connected with active or passive elements, the cable strands must
be sealed with resin filled heat-shrink tubing.
The preventive safety marker band (DW 135 S) is not installed in locations where
the pipeline crosses roads, rivers, or bridges.
At such intersections the insulated cable can be installed in two ways:
- The insulated cables are glued to the pipeline which
then receives a protective covering
- The insulated cables along the pipeline are installed
in a protective piping of their own)
|